The contractor building Fayetteville’s minor league baseball stadium is asking for nearly $1 million more from the city to get the project built on time and to cover expenses blamed on Hurricane Florence. The additional costs would be on top of an already rising price tag for the stadium, now at $40.2 million.Barton Malow Co. has told the city it is behind schedule because of the September hurricane and other rain delays, according to recent correspondence between the contractor and […]